Sunday, July 6, 2014

Happy Fourth of July Weekend

The pool crew did come on Friday as I said to deliver the spa and work on the pool cleaning. I was so grateful that they were willing to work some on this holiday. Later that day Lauren and Maek came over to eat lunch  with us. We grilled burgers with all the trimmings and frah field corn on the cob and baked beans.  After resting a bit we all got in the pool. So neat. We floated and relaxed until the sun was past the pool. We all dried off and for out the ice cream freezer and made homemade ice cream. I had a pound cake and fresh blueberries, cherries and strawberries to go with the ice cream. Needless to say no one went to bed hungry. 😀
Saturday we just relaxed around the house. I made a quick to Jackson to swap out the bassinet mattress. I shopped a little too. Ha!  Sunday was another quiet day.  We did get back in the pool. I think once the concrete is poured it will be so nice. 
This week looks to be a busy one. Fence people should be here, pool crew has the last things to wrap up. I'll keep you posted s
See ya,
Di

Friday, July 4, 2014

Day 18. Spa Delivery

This morning we got to see the spill over spa delivered and set in place. It's not hooked up yet but it will be next week. The pool crew also worked on cleaning the pool.  
After waiting the "required" amount of time we got in the pool. Four floats and four floaters. Ahhh lovely. And one goofy beagle. She didn't want in the pool but she didn't like being out of the pool. Mark put her in for a few minutes but she was very unhappy, and then promptly rolled in the dirt!  Yep bathtime for her.  
Next week will include connecting the spa, adding a small concrete trench around the edge of the pool, placing the brick coping, then pouring the new patio, bricking around the spa and  smoothing the yard around the pool.  The end is so near.  We can't wait. It has been so much fun to watch this dream come true. 
Great July Fourth. 
We grilled burgers and hotdogs for a late lunc along with fresh boiled corn, and baked beans.   After our swim we made homemade ice cream with fresh blueberries, cherries and strawberries and pound cake! Can we say stuffed to the gills! 
See ya, Di


Thursday, July 3, 2014

Day 16 and 17. Very Little Progress

Wednesday we only had someone come by to check the pump.  I understand, there are people that had their pools started long ago and they are planning a big pool party for July 4th. We were never suppose to be ready for the 4th so we are really ahead of the schedule. Do I want my pool all ready to enjoy? Heck yeah but I am an adult and I can wait. I've tried not to whine too much. But I am hoping we can at least get in the pool some tomorrow afternoon. We did hear from Brian today and they will be here in the morning to set up the spa and vacuum the pool. So it's looking good for an afternoon swim. Sounds good to me. 
See ya,
Di

Tuesday, July 1, 2014

Day 15. Good Things Come to Those Who Wait.

Today I had a meeting in Jackson to work on school stuff so I had to rely on Paul to keep me posted on the pool progress. About 1:30 I get a text that the electrician was connecting all the pool equipment. Also that should mean the rest of the pool crew would be coming to work soon. 

And soon this happened. 
And then this.
The equipment trench was filled in  and the area around the pool was filled in more completely. 

Great progress was made today.   The spa has finally arrived from Canada and will be delivered tomorrow. Yeah!  We are adding more water so the pumps can be turned on and start cleaning the pool. Water level reached the point where we could turn on the pump. First attemp was a scary moment. Water started pouring out of the pump. Hmmm I don't think that is what it's suppose to do. Call or text Brian.  A few minutes later we get a text to make sure the black knob is on filter. Nope it was on waste. Knob turned to filter, turn pump on, wait, wait... I hear bubbling from air in the lines. Soon another valve starts bubbling, then all settles down and it's purring like a kitten. We have success. 

On another note, a WC student that has  been in Vanderbilt Hospital battling cancer, came home today.   She will go to Bateson soonto continue her treatment but coming home was a great day. She lives just a few houses down the street. She was welcomed home by a great crowd of friends. Prayers have been answered. Prayers for her continued improvement. 
See ya, 
Di 

Monday, June 30, 2014

Day 14. Yes We Did

Beautiful sunny day☀️ and very quiet. 😞 I expected to hear noises coming from the back yard but no such luck. I realize we are not the only pool being built so I'll be good. And wait. 
Paul had jury duty today so this morning I had the house to myself. I started sewing on the bassinet lining, under skirt and outer skirt. It is looking so pretty. It took 14.5 yards of lilac tuilie to make the under skirt. I hope it turns out as pretty as I envision. 
By late afternoon, I was positive no one was coming to work today so I put on my swimsuit, grabbed my float and a towel and headed to the pool. Yep I got in. It was great. I had to be careful since it's still just dirt all around the pool but it was great. I floated and splashed from one end to the other end. 🏊
After Paul finished mowing the yard he took a dip in the pool too!  We can't wait to have everything all set up. 
See ya, Di 

Sunday, June 29, 2014

Day 13. Quiet Day

Today's progress seems to be just watching or more like listening to the water run as it fills up the pool. I just checked a few minutes ago and looks like about 9 more inches to reach the bottom of the skimmers. Beautiful sunny day so I hope any of the "muddy" spots are drying up as I write. We really need a busy day tomorrow while we have drier weather. 
See ya, Di

Saturday, June 28, 2014

Day 12. Happy Noises



9:00 arrived with the glorious sound of workers making progress. So happy to see the sun and hear workers noise. I'll share pictures later. And you know there will be pictures. 
Okay here are a few pictures. The pad now has the pump, heater and the salt converter. You can also see the pipes that wil soon be connected to the pool. 
See ya, Di 




Friday, June 27, 2014

Day 11 Rain, Rain Go Away.

Steady light rain falling this morning, so no work will be happening this morning. Kevin of Sharpe HVAC did come by and reconnect our AC. That is a big plus. We can go back to our bedroom and stay cool all day. Now just hoping  for some dry weather to get this party started.  
On another note I spent most of yesterday sewing the window treatment for the nursery. I can't wait to see it hung up. I'll post pictures later. 
See ya, 
Di 

Thursday, June 26, 2014

Day 10 A Small Step Backwards

Well we had a little activity earlier this morning. Apparently the underwater lights had a very small leak that had to be repaired. This meant draining the pool to below the lights 😢 and then sealed again. 
I guess since most of the pool walls are curved it is harder to get a tight seal than on a flat wall. Earlier I mentioned that a very large crepe myrtle tree had to be removed, and it had some roots under the concrete pad that the AC unit was sitting on. As it was removed it cracked and broke the AC pad. So since the pool equipment has to sit on a concrete pad they poured a new pad large enough for both pieces. Unfortunately this meant the AC unit had to be disconnected. On the up side we are lucky we have a second AC unit for the other bedrooms and upstairs. So even though it hasn't been as cool in the house it has not been too bad. Hopefully first thing in the morning we will have our AC reconnected and back on. 
Also that should mean the pump can be installed for the pool and the lights put back in. Yeah!!! I hope we have lots of progress tomorrow. 
See ya Di

Wednesday, June 25, 2014

Day 9 Late Start Day

All was quiet after a predawn rain. We thought no work would happen today. All of a sudden we hear tractors moving in the back yard. Brian and the crew showed up to dig the line from the pool to the pump. At the same time several guys were putting the skimmers in place. Also Brian was on another tractor filling in the trench behind the pool walls and smoothing out the ground. Love this progress!  
You can see the mud pit where our patio was located. Yuck. 
We also have some new yard art!  So proud to advertise for this great company. 
Here is the last picture for the day.   It's kinda hard to see but this is where the pump and other equipment will go along with our AC unit. So for  tonight we will only have one AC unit. Hmm maybe need to sleep in one of the other bedrooms tonight. 
See ya, 
Di